Located in Casper Wyoming, “The Hunting Energy Project” was designed for a building used for servicing oil and gas mining equipment.
The nature of the facility required a high ventilation rate, to improve both the quality of the work environment as well as productivity.
How to improve ventilation without breaking the bank.
The Engineer of record, using all the resources available to him, performed a detailed economic analysis. He compared three commercial options: DualCore®, Standard Technology and a Standard MUA.
By Analyzing First Cost, Annual Operating Cost, Payback, Internal Rate of Return (IRR) and most importantly Total Present Worth ( Net Present Value) a complete Life Cycle cost was performed.
When operated at a 24/7 duty cycle, the results were impressive.
The Tempeff DualCore® ERV was the only true option. The equipment clearly showed the best Life Cycle Value. The Net Present Value was almost half of the compared alternate ERV. The DualCore® operating cost is 69.5% lower than the alternate ERV and 83% less than a standard make-up air unit.
On the strength of the Engineer’s detailed analysis, Hunting Energy purchased Two Tempeff DualCore® Energy Recovery Units.